April 2020

April 2020

  • Landscaping and paving complete
  • Interiors complete
  • Bridge craned into position
  • Completion
March 2020

March 2020

  • Roofing complete
  • Flooring and painting complete
  • Second fix plumbing and electrics
  • Bar and cellar fitted
  • Interiors start
February 2020

February 2020

  • The roof in place and Cedar shingles go on
  • Underfloor heating is laid
  • Timber cladding of walls starts
  • First fix electrics and plumbing complete
January 2020

January 2020

  • External lower brickwork complete
  • Roofing and wall framework goes up
December 2019

December 2019

  • Steelwork erected
  • Beam and block floor laid
November 2019

November 2019

  • Concrete pumped in
  • Steelwork bolt boxes set into position for beam and block floor
October 2019

October 2019

  • Tipis dismantled
  • Site cleared, footings dug and inspected